Activity-Set-Status method

Activity A calls Activity B.

Activity B's steps include:

  • Step 7 - use Activity-Set-Status to set a Fail status.
  • Step 8 (the last step in the activity) - does a Page-Remove of a temporary page.

Questions:

  • Will Step 8 reset the value of pxMethodStatus to Good?
  • The Help File for Activity-Set-Status says "The message is added to the page."  After step 8 completes successfully, will the message be removed from the page?