hi,
Our application is in production and as part of new development , we have added lot of new stages to the case. now how this will impact the open cases in production.
after we migrate the new code to production , how the in-progress cases will behave. we are in 7.2.2.
any ideas on this please.
Hi Veera,
Are you sure that there are no changes made to the existing stages and flows? I did a quick test at my end. With the addition of new stages, I could not see an impact on the existing cases. However, any modifications to the existing flows/stages, would have.
However, we recommend you to test in your lower environment with dummy old cases, before you migrate to production.