Question

3
Replies
472
Views
Veerappan Rathinam (Developer85)
Virtusa Inc

Virtusa Inc
US
Developer85 Member since 2014 34 posts
Virtusa Inc
Posted: May 8, 2018
Last activity: July 10, 2018
Posted: 8 May 2018 16:23 EDT
Last activity: 10 Jul 2018 6:02 EDT
Closed

Agile Studio not showing Burndown chart

Hi, We are using Agile studio for tracking the development progress in our project. The Burndown chart is not showing the Actual progress (Blue Line). But the daily task updates are properly getting tracked by the Agent (brundown). we have provided proper start date and end date for each sprint.

any Idea why this is happening. ?

Low-Code App Development Case Management Project Delivery
Moderation Team has archived post, This thread is closed to future replies. Content and links will no longer be updated. If you have the same/similar Question, please write a new Question.