Why does pega not allow to change to current stage in Pega 7.1.7?

We have 4 steps under one stage and when I try to use change stage from Step 4 I expected the case to start from Step 1 of the stage. But it shows me an error that I cannot use change stage to jump to current stage.

When I tweak the code in pxchangestage it works. Any leads on why Pega restricted it and what is the best way to implement this approcah?