Date Mismatch in Pega 5.5 and and 7.19

In pega 5.5 application all front end dates are in PST time where as clipboard Dates are in GMT, but in 7.1 front end dates showing as GMT-8, ie If date in clipborad is 01312017000000GMT in front end it is 01302017. How to fix this?

***Updated by Moderator: Marissa to update categories***

Data Integration Java and Activities User Experience
Moderation Team has archived post,
Close popover This thread is closed to future replies. Content and links will no longer be updated. If you have the same/similar Question, please write a new Question.