Hi,

Due to some exception, my CASE is in FlowProblems flow, then with other actions - Change stage,

I am trying to change to other stage, which will also clean up processes if is see the post flow action of that flowaction.

Now, the issue is it is changing stage properly but it is not is not deleting the problem assignment, is it expected?

I am thinking this problem flow is not part of case flow so pxChangestage will not clear the problem assignment.

Regards

Gouri Shankar K