GETNextWork_MoveAssignmentToWorklist set to false but not working

Using v7.1.9., we had requirement to no to move to worklist when user clicks GetNextWork, so in help i read you can achieve this using GETNextWork_MoveAssignmentToWorklist system setting. i overwrite this in my application ruleset, but it is still not working.

When i analysed what is happening, looks like in pega FINAL OOB activity Assign-.MoveToWorklist in set 4 they are calling this system settings, but ruleset is hardcoded as Pega-Procom and this activity is Final...

Now how to address my requirement please ?

***Updated by moderator: Lochan to update Categories***

Low-Code App Development Case Management
Moderation Team has archived post,
Close popover This thread is closed to future replies. Content and links will no longer be updated. If you have the same/similar Question, please write a new Question.