How to add parallel steps in a process in case designer

Ex: I am having 4 steps (Step1 , Step2 , Step3 , Step4) under a single stage.

i need Step1->(Step2 or Step3) --> Step4

Step 2 and step 3 are parallel.

In 7.1, we have step configuration option. We can select 2 or more steps as parallel steps by selecting Start step upon stage entry.

How to achieve this in 7.2.2.