How to calculate SLAs for this scenario?

-
The answer for below is 60. Please explain why? Thanks on advance.
A service level agreement rule describes the following behavior:
Urgency AdjustmentInterval lengthLimit
Start of service level20
Goal interval108
Deadline interval2024
Passed Deadline interval20243

The service level provides a four-hour initial delay. If the case urgency (.pxUrgencyWork) is set to 10 and the case reaches the assignment at 9am Monday, what is the assignment urgency at 12pm Wednesday?