How to deploy purge/archive settings?

Is there any way or recommendation to release purge/archive settings to production? We would like to test purge/archive in development/test environment, and then import to the production. Is it possible? Or do we have to configure it on production directly?

As far as I checked, an archival settings is an instance of Data-Admin-ArchiveSettings, and the schedule is configured in work object which is instance of PegaAccel-Management-Archival. It seems that we can export these instance (and assignment?) in a package and import the package to another environment. Is there any concern on this?

***Moderator Edit-Vidyaranjan: Updated Platform Capability***

Data Integration
Moderation Team has archived post