Question

4
Replies
3384
Views
venkateswarareddk Member since 2015 1 post
Infomaticscorp.com
Posted: 3 years ago
Last activity: 3 years 3 months ago
Closed
Solved

How to set a parallel process with respect to a step ?

In 7.1.x version had a provision to set a step as parallel using the step configuration. how this can be achived in 7.2.2.

Ex: I am having 6 steps (Step1 , Step2 , Step3 , Step4 , Step5, Step6 ) under a single stage.

& i need Step1->Step2->Step3 as sequance

Step4 need to parallel to Step3 : Step3 || Step4

again step5 || Step6 are parallel

Design:

Step1

Step 2

Step 3 Step4

Step 5 Step6

I tried with "Add Parallel process" next to the respective steps .But it executes when the stage starts not to the particular step.

"Start When" is that a option ? Kindly guide me with Screen shot !

Case Management
Moderation Team has archived post
Share this page LinkedIn