Information on Stream Nodes processing

Hi Team,

We are running pega8.1.3 version, we have 2 stream nodes in our environment. My question is what will happen if any job is running on one of the stream node and for some reason that node went down. Will that job again get queued to available node? Or what will happen to the job? Will it fail or re-queue? Please let me know if my understanding is correct (job will re-queue)?  Thanks & Regards,