Invalid datetime format/Invalid datetime "06/01/2016 00:00:00"

Hello,

We have migrated from pega 7.1.9 to pega 8.2.

Our connector doesn't work since we migrated :

Invalid datetime format/Invalid datetime "25/08/1990 00:00:00" 

Connectors add double quotes to the datetime value properties : "25/08/1990 00:00:00"

Before the migration, the result of the connector was 25/08/1990 00:00:00

Every connectors with a datetime property are now defined with double quote.

Pega technical team ask us to add @String.replaceAll(.defaultResponse_GET,"\"","") but i don't think it's the best solution to replace quotes.

Does anyone encountered the same issue ? Why did the date format has changed from pega 7 to 8 ?

Thanks you for your help.