jumpToTask activity is not working as expected

I created a button which calls jumpToTask activity followed by refresh harness on clicking it





and this is what i got when i clicked the button, it jumped to the assignment but it is not letting me do anything.


I created a button which calls jumpToTask activity followed by refresh harness on clicking it

and this is what i got when i clicked the button, it jumped to the assignment but it is not letting me do anything.

but if you remove the refresh harness action from the action set and manually click the refresh option from the actions menu(below image) after running jumpToTask activity(by clicking the button), it works as expected.

I used the same configuration used in the refresh option found in the Actions menu, also no errors in tracer.