Pega is saving date which is one day off

We have few DATE properties. When the same properties are saved into the DB, the saved date is one day off. For ex: if the clipboard property is showing as 20160701, the data is saved in DB as 30-JUN-2016 (20160630). I can see in tracer that Pega is passing the date as one day off to merge command and it includes time like 20160630 20:00:00. How to fix this issue?