Hello!
We change production level from 2 to 5 in system instance and restart the server (including removing extract marker).
However, flows with enabled draft mode are still being executed correctly.
Is this normal behavior? PDN says that draft flows are not allowed on production level 5 systems.
Thanks,
Yuriy Berdnikov
**Moderation Team has archived post**
This post has been archived for educational purposes. Contents and links will no longer be updated. If you have the same/similar question, please write a new post.
Hi Yuriy, Good Morning!
>>> We change production level from 2 to 5 in system instance and restart the server (including removing extract marker).
could you please confirm the values on clipboard page. A restart should take effect on this change.
>>> However, flows with enabled draft mode are still being executed correctly.
they should be ignored.
>>> Is this normal behavior?
No, Draft option enabled flows will be ignored in Production system.
also please refer: https://pdn.pega.com/process/troubleshooting-fail-to-compile-generated-java-for-flows-in-draft-mode-on-production-system
could also please specify PRPC version?
Please share your thoughts/comments, Thank you!