Replacing current harness with work object
I have a button on my screen on clicking of which I am launching a flow using Create Work method. It is opening the work item in new tab. I want to replace the harness with the work object. It should not go to the next tab.
Hi Sandeep,
May be you can try with Launch Harness with Replace Current target to achieve your requirement.
Regards
Mahesh