Question

2
Replies
234
Views
abdul qaadir (abdulq95)
JP Morgan

JP Morgan
US
abdulq95 Member since 2014 20 posts
JP Morgan
Posted: February 22, 2017
Last activity: April 6, 2018
Posted: 22 Feb 2017 21:58 EST
Last activity: 6 Apr 2018 19:26 EDT
Closed

Rollback approach for upgrade

We are upgrading our prod environment over this weekend from pega62sp2 to PEga72.

As part of rollback we have below approach:

1. Take DB backup of Pega62sp2 schema (rules +data)
2. Perform upgrade on split schema.
3. Incase of rollback.
4. Restore the Pega62sp2 DB backup .

Let us know if this approach holds good and is there anything else to be taken care.?

We have tested it in SIT environment and rollback went fine.

**Moderation Team has archived post**

This post has been archived for educational purposes. Contents and links will no longer be updated. If you have the same/similar question, please write a new post.