We are upgrading our prod environment over this weekend from pega62sp2 to PEga72.

As part of rollback we have below approach:

1. Take DB backup of Pega62sp2 schema (rules +data)
2. Perform upgrade on split schema.
3. Incase of rollback.
4. Restore the Pega62sp2 DB backup .

Let us know if this approach holds good and is there anything else to be taken care.?

We have tested it in SIT environment and rollback went fine.

**Moderation Team has archived post**

This post has been archived for educational purposes. Contents and links will no longer be updated. If you have the same/similar question, please write a new post.

System Administration Upgrades
Moderation Team has archived post,
Close popover This thread is closed to future replies. Content and links will no longer be updated. If you have the same/similar Question, please write a new Question.