Transfer in Escalation Action not working after deadline

Hi,

I have an requirement wherein a assignment will be pended for some time using local action.

Then, assignment moves from Work Basket A to Work basket B.

When the goal & deadline time are elapsed, I called an escalation action " Transfer ".

Now, as per transfer action, assignment should be moved from Work Basket B to Work Basket A. 

But here the Transfer action is not happening. I tried reassigning using activity too, but its not working. Any suggestions please.