Question

12
Replies
1193
Views
KARTHIKD Member since 2012 17 posts
Capgemini
Posted: April 21, 2016
Last activity: April 27, 2016
Closed

BIX Extract Error due to data issue. How to easily identify the work item causing the issue?

Hi All,

Pega Product Version : PRPC V6.3 SP1

We are doing daily bix extraction of the work items in our production system. We received the following error today during the extraction process and bix extract rule execution history showed the below error.

"Could not process : String was not a datetime".

We have sorted out all the work items eligible for today's extraction and compared it with the Bix file extracted today to compare in which work item it is failed. This is a manul task and time consuming.

Is there any way we can find out easily, in which work item(probabaly, pyid or pzinskey of the work item) the extraction failed?

Data Integration Reporting System Administration
Moderation Team has archived post