when user B tries to open his/her assignment, PRPC says the work is still locked and under modification by user A

Our customer (on 7.1.9 / PegaCloud production environment) is experiencing the similar issue - not sure it's the same.

After user A finishes his assignment & submits it, PRPC routes it to user B then.

The issue is that when user B tries to open his/her assignment, PRPC says the work is still locked and under modification by user A.

Is this symptom potentially the same as what's explained above, if yes, does user B need to wait for 2 hours max (or 30 sec max?)

*Default locking is selected as case lock configuration.

Message was edited by: Marissa Rogers - branched to its own thread, added category